Usoi Dam Wave Overtopping and Flood Routing in the Bartang and Panj Rivers, Tajikistan |
By John Risley, Joseph Walder, and Roger Denlinger |
Water-Resources Investigations Report 03-4004 |
Prepared in cooperation with U.S. Agency for International Development,
|
ONLINE ONLY |
AbstractThe Usoi dam was created in the winter of 1911 after an enormous seismogenic rock slide completely blocked the valley of the Bartang River in the Pamir Mountains of southeastern Tajikistan. At present the dam impounds 17 million cubic meters of water in Lake Sarez. Flood volume and discharge estimates were made for several landslide generated floods that could overtop the dam. For landslide volumes of 200, 500, and 1,000 million cubic meters, estimated overtopping flood volumes were 2, 22, and 87 million cubic meters of water, respectively. Estimated peak discharge at the dam for these three flood scenarios were 57,000, 490,000, and 1,580,000 cubic meters per second, based on triangular hydrographs of 70-, 90-, and 110-second durations, respectively. Flood-routing simulations were made for the three landslide-induced overtopping floods over a 530-kilometer reach of the Bartang and Panj Rivers below the Usoi dam. A one-dimensional flow model using a Riemann numerical solution technique was selected for the study. A constant 50-meter wide rectangular channel, which represented the mean channel width, was used for the entire reach. A roughness coefficient of 0.038, appropriate for steep mountainous streams, also was used for the entire reach. For the 87 million cubic meter volume overtopping flood scenario, the peak flows were approximately 1,100, 800, and 550 cubic meters per second at locations 50, 100, and 150 kilometers downstream of the dam, respectively. The model was also used to simulate the less likely scenario of an instantaneous dam breach and draining of the total volume of the lake. Simulated peak flows were approximately 64,000, 52,000, 40,000, and 20,000 cubic meters per second at locations 50, 100, 150, and 530 kilometers downstream of the Usoi dam. |
|
ContentsAbstractIntroduction Purpose and Scope Description of the Study Area Acknowledgments Probable Flood Hydrograph Determination Landslide-Generated Floods Dam Breach Flood Flood Routing Model Selection Model Description Channel Configuration Roughness Coefficients Simulations Limitations Summary and Conclusions References Cited Appendix A: Alternative Investigation Appendix B: Method of Estimating the Starting Hydrograph for the Overtopping Flood Scenarios Appendix C: Method of Estimating the Starting Hydrograph for the Dam-Breach Flood Scenario |
|
Download the report (PDF, 1 MB) (Adobe Reader® required; version 5 or higher preferred.) If you do not have the Adobe PDF Reader, it is available for free download from Adobe Systems Incorporated. Document Accessibility: Adobe Systems Incorporated has information about PDFs and the visually impaired. This information provides tools to help make PDF files accessible. These tools convert Adobe PDF documents into HTML or ASCII text, which then can be read by screen-reading programs that synthesize text as audible speech. In addition, a version of Adobe Reader that contains support for screen readers is available. The conversion tools and the accessible reader may be obtained free from Adobe through their conversion tools Web site.
|
Accessibility FOIA Privacy Policies and Notices | |