TABLE B-9 - CAPITAL COST ESTIMATE (U.S.$, Installed at a U.S. Gulf Coast Mine-Mouth Location) Source: U.S. Engineering Firm - 1991
| ITEM | LIGNITE | BITUMINOUS | REMARKS |
| Process Equipment Cost | |||
| Briquetting Machines | 1,500,000 | 1,500,000 | Source: Manufacturer |
| Coal Pulverizer | 44,000 | 44,000 | Conventional Power Plant Type |
| Clay/Coal Mixer | 112,000 | 112,000 | |
| Additives Mixer | 224,000 | 224,000 | |
| Briquet Aftertreater | 300,000 | 300,000 | Shaft Dryer |
| Lignite Pulverizer | 1,656,800 | 0 | |
| Associated Equipment | 200,000 | 200,000 | |
| Subtotal | 4,036,800 | 2,380,000 | Process equipment cost, delivered |
| Process Equipment Erection | 10,092,000 | 5,950,000 | 2.5 Multiplier to erect and complete |
| Auxiliary Equipment Cost | |||
| Clay Storage | 320,000 | 320,000 | Reinforced Concrete Silo |
| Raw Coal Storage | 0 | 0 | |
| Lime Storage | 160,000 | 160,000 | Reinforced Concrete Silo |
| Water Tower | 189,000 | 189,000 | Elevated Steel Tank |
| Subtotal | 669,000 | 669,000 | Auxiliary Equipment Completed |
| Auxiliary Erection | 602,100 | 602,100 | 0.9 multiplier to complete |
| TOTAL PROCESSING | 15,399,900 | 9,601,100 | |
| Additional Costs | |||
| Plant Commissioning | 100,000 | 100,000 | Allocated Amount |
| Land Acquisition | 200,000 | 200,000 | Ten Acres at $20,000/acre |
| Land Clearance | 50,000 | 50,000 | Allocated Amount |
| Subtotal | 350,000 | 350,000 | |
| TOTAL PROCESS PLANT | 15,749,900 | 9,951,100 | |
| Contingency, 10% | 1,574,990 | 995,110 | |
| TOTAL INVESTMENT | 16,975,000 | 10,946,000 | (Rounded) |
| NEXT |
Created by the EERT WWW Staff.
[an error occurred while processing this directive]