TABLE B-9 - CAPITAL COST ESTIMATE (U.S.$, Installed at a U.S. Gulf Coast Mine-Mouth Location) Source: U.S. Engineering Firm - 1991
ITEM | LIGNITE | BITUMINOUS | REMARKS |
Process Equipment Cost | |||
Briquetting Machines | 1,500,000 | 1,500,000 | Source: Manufacturer |
Coal Pulverizer | 44,000 | 44,000 | Conventional Power Plant Type |
Clay/Coal Mixer | 112,000 | 112,000 | |
Additives Mixer | 224,000 | 224,000 | |
Briquet Aftertreater | 300,000 | 300,000 | Shaft Dryer |
Lignite Pulverizer | 1,656,800 | 0 | |
Associated Equipment | 200,000 | 200,000 | |
Subtotal | 4,036,800 | 2,380,000 | Process equipment cost, delivered |
Process Equipment Erection | 10,092,000 | 5,950,000 | 2.5 Multiplier to erect and complete |
Auxiliary Equipment Cost | |||
Clay Storage | 320,000 | 320,000 | Reinforced Concrete Silo |
Raw Coal Storage | 0 | 0 | |
Lime Storage | 160,000 | 160,000 | Reinforced Concrete Silo |
Water Tower | 189,000 | 189,000 | Elevated Steel Tank |
Subtotal | 669,000 | 669,000 | Auxiliary Equipment Completed |
Auxiliary Erection | 602,100 | 602,100 | 0.9 multiplier to complete |
TOTAL PROCESSING | 15,399,900 | 9,601,100 | |
Additional Costs | |||
Plant Commissioning | 100,000 | 100,000 | Allocated Amount |
Land Acquisition | 200,000 | 200,000 | Ten Acres at $20,000/acre |
Land Clearance | 50,000 | 50,000 | Allocated Amount |
Subtotal | 350,000 | 350,000 | |
TOTAL PROCESS PLANT | 15,749,900 | 9,951,100 | |
Contingency, 10% | 1,574,990 | 995,110 | |
TOTAL INVESTMENT | 16,975,000 | 10,946,000 | (Rounded) |