USGS
 Environmental Geochemistry and Sediment Quality in Lake Pontchartrain

Sediment Sampling Surveys (con't)

Box and Push-Piston coring-

Objective and Accomplishments:

As mentioned earlier, sediment coring methods are dependent on task objective and environmental parameters. For contaminant studies there exists a strong desire to retain a chronology of deposition in the sediment sample. Usually only recent sediments (<100 years accumulation) are sampled and a non-disturbed section is crucial. Most coring methods in contaminant studies are designed to recover the top meter of sediment, to retain integrity to laminations or bedding and to minimize agitation of the sediment surface (Figure 12). Box and push-piston cores enter the sediment slowly, under the weight of gravity or gentle downward force. As a result they do not disturb the sediment within the barrel, but cannot penetrate as deep as other coring methods. Box and piston cores usually have an access to the core that allow subsampling to proceed onsite without further disturbance of the sediments

Figure 12:

techniquefig12a.gif (100288 bytes)

 

Figure 13:

techniquefig13a.gif (26810 bytes)

In September 1996, 9 piston cores were acquired from the vessel G. K. Gilbert along the Lake Maurepas tidal delta and the southern edge of Lake Pontchartrain (Figure 13). The cores were taken with a modified push corer that could be operated over the side of the boat and was capable of retrieving 1 meter long cores. The following year, 26 cores were obtained throughout Lake Pontchartrain using a 0.1m2 x 1m box corer. The top 8cm of each core was subsampled 2-3 times with 1 foot long, 4 inch diameter polycarbonate core liners.

In June 1998 over 70 box cores were acquired from Lake Pontchartrain. Thirty of the box cores reoccupied sites from the previous year and were subsampled in a similar fashion. Sixteen of the box cores were taken from sites previously sampled with the underway surficial sediment sampling method described below. At these sites three box cores were acquired per site and each core was subsampled using the 4 inch core liners in 2cm intervals down to 10cm. The remaining 24 box cores were subsampled in a similar fashion, except sampling proceeded down to 16cm. These cores where acquired from areas interpreted to have high concentrations of trace metals in the sediments, based on previous sediment surveys. Dredge pits along the southern shore of the lake were also targeted. The samples were frozen to retain organic carbon.

In addition to sampling with the foot long core liners, up to one meter long subsamples were taken from 16 of the box cores using 4 inch diameter, meter long pvc pipe that was pushed into the sediment, capped and retrieved. These subcores were split into two halves along core, one half was stored whole, the other half was subsampled as described in the methods section below.

The task objective of the box and piston-core surveys was to establish a surface and downcore trace metal contaminant throughout the lake. The sediments were analyzed for 30 different elements related to anthropogenically-derived contamination. Additionally, radioactive isotope-decay rates (Berrilium-7) were measured downcore to determine sediment accumulation patterns within the basin. Results of these analyses can be used to define hot spots of contaminant accumulation within the lake. Accomplishments to date include a plot of recent sediment accumulation rates throughout Lake Pontchartrain that can be compared with other models of physical parameters that affect sediment distribution, such as water current patterns or floodwater discharge into the lake. Also, downcore metal profiles provide a baseline distribution of contaminants throughout the lake as well as an indication of whether the sediments have been reworked since initial deposition. Further studies of the sediment samples include efforts to evaluate the validity of the underway surficial sediment sampling system through correlation with surficial material retrieved from the box cores. Also, downcore pollen assemblages will be studied to provide a history of regional changes in vegetation (Figure 14). Finally, the meter long sub cores retrieved from the box cores will be x-rayed to detect evidence of laminations and bioturbation within the sediments. This information will provide insight into accumulation and mixing patterns in the near surface.

Figure 14: techniquefig14a.gif (21341 bytes)


Method:

The box core rig used in this survey is a 0.1m2 by 1 meter open-ended stainless steel box attached by sleeves to a steel frame. When the frame is lowered by cable to the sea floor, the box slides down the sleeves and penetrates the sediments under force of gravity, usually assisted by lead ballast attached to the box support. Upon retrieval, tension on the cable pulls two steel spades together under the base of the box, thereby preventing sediment loss. Once on deck, the sediment in the box can be subsampled through a lid at the top. Several one-foot long, four inch diameter polycarbonate core liners are then inserted vertically into the sediments and removed by hand. After removing the overlying water, sediments from these subcores are extruded using a PVC piston inserted into the bottom of the core liners. While holding the core liner vertical, the sediment is extruded out the top by gently forcing the piston upward. For these studies the sediment was sampled in 1-2cm thick intervals up to 16cm depth. Interval thickness is measured by placing a ring of the appropriate thickness on top of the core liner. When the sediment reaches the top of the ring, a thin aluminum plate is inserted between the ring and core liner. The plate is carefully removed to avoid disturbing the underlying sediment (Figure 15). The sample is then placed in a labled ziploc bag for storage, samples designated for organic carbon study were frozen.

Figure 15:

techniquefig15.gif (104336 bytes)

Additional sampling included four inch diameter, one meter long sections of PVC sewer pipe, cut into two halves length-wise. The two halves were recombined with duct tape and inserted into the box core. The bottom of the pipe is capped and the subcore is retrieved by hand. On deck the tape is cut away, end caps are provided and the subcore is split lengthwise using a hack-saw blade to produce two subcore halves. One half is sealed in plastic wrap and archived. The other half is sectioned into one-inch intervals downcore. Each interval is removed and placed into a labled ziploc sample bag. These samples were later frozen.

The piston core is a PVC barrel with an inner barrel that can be pushed into the sediment using attached handles. The corer can be operated over the side of the boat and is capable of retrieving 1 meter long cores. Once the inner barrels are onboard and removed, they are capped, inspected for quality, and measured. During retrieval and transport, the cores are kept vertical at all times to minimize surface disturbance. At the lab, a PVC piston was inserted in the bottom of the core liner and the core is placed on a stand designed to hold it stationary while a hydraulic jack is used to raise the piston and extrude the sediment out the top of the core barrel. A ring of the same diameter of the core barrel, cut to the appropriate height, is used for measuring the thickness of each interval. When the sediment reached the top of the ring, a thin aluminum plate was inserted between the ring and core liner. The plate was carefully removed to avoid disturbing the underlying sediment.

 

Back to Table of Field Investigations

Forward to Grab Samples


Beginning of Section
New Field Sampling Techniques

 

[an error occurred while processing this directive]