Glossary
- Accuracy Ratio or Error
Ratio
- The error ratio is a means of expressing the magnitude of the error of the
survey in relation to the distance traversed by the survey. Intuitively, a
unit of error is of greater importance in a short traverse than in a longer
traverse.
- The error ratio is expressed as the quotient of the absolute value of the
error and the distance traversed. Always give the value with "1" in the
numerator.
-

- The permissible error ratio
depends on the accuracy required for the survey. Ordinary taping
generally refers to work for which the error ratio does not exceed 1/5000. An
accuracy ratio of 1/3000 may be allowed for rougher work, but there is very
little additional care needed in the procedures to attain the 1/5000 level. An
accuracy ratio of 1/10,000 can be achieved by paying careful attention to
details.
- Add Tape
- An add tape has an additional major division at the head, beyond
the zero mark of the tape, which is subdivided into finer graduations, usually
in tenths of a foot (or meter), sometimes in hundredths. The use of this tape
requires that the minor reading be added to the major division reading.
- Some tapes have minor divisions at both the head and tail.
- Adjustments
- Since all real measurements are imperfect, some amount of error will
accumulate in the course of a survey. That error can be logically distributed
throughout the survey by various adjustment procedures (i.e., manipulation of
the data to produce a more logical result). Adjustments can and should be done
with any set of measurements for which error can be assessed.
- Adjustment procedures do not correct the errors in the
measurements. They simply produce a set of data that is self-consistent (e.g.,
the starting and ending points of a closed-loop leveling circuit have the same
elevation - which is physical reality). The adjusted values are not
necessarily true - they are just likely to be closer to the true
values than the original measurements.
- Azimuth
- The angle to a line of sight, measured clockwise from (usually) a north meridian.
- Backsight
- A backsight is a reading taken on a position of known
coordinate(s). Since a survey progresses from a point of known position to
points of unknown position, a backsight is a reading looking "backward" along
the line of progress.
- The first reading of almost any survey job should be a backsight onto a
fixed point of reference, usually a benchmark
of some sort.
- (Compare to foresight).
- Baseline
- A baseline is a line used for reference in a survey job. It is often a
centerline or a street line. A baseline is not necessarily straight; e.g., the
centerline of a street or pipeline will often curve. The important aspect is
that the baseline can be precisely located, then used for referencing other
measurements on the job site.
- Selection of a baseline is entirely arbitrary. However, judicious
selection can make the rest of the job much easier.
- Bearings
- Bearings are used to indicate angular orientation with respect to the
earth. Bearings consist of three components:
-
- The cardinal direction of the nearest end of the meridian (N or
S);
-
- The angle measured from the nearest end of the meridian;
-
- The cardinal point indicating the direction of deflection from the
meridian (E or W).
- The angular measure is always within the range of 0-90 degrees.
- Benchmarks
- A benchmark (BM) is permanent marker (usually a bronze
disk) at a point of determined location (elevation and possibly horizontal
coordinates). In a less formal sense, it is a point of fixed location (such as
a mark on a bridge abutment, a foundation, or a rock face). It can be used as
a reference point for surveys in its locality. Descriptions of benchmark
locations and their elevations are published by government agencies.
- A temporary benchmark (TBM) is a point of fixed location
that is used as a reference for a short-duration project. Its elevation may or
may not be determined with respect to a larger coordinate system. A
TBM could be something like a nail in a tree or fencepost, a
mark on a curb, or a sturdy stake driven in an out-of-the-way area of a
project site.
- Booking Values
- Booking
simply means "entering the field data in the field book". A
format appropriate for the type of survey should be followed to make
interpretation and retrieval easy.
- Breakpoints
- A breakpoint is a point where a change in some parameter of
interest occurs. In surveying, breakpoints are usually associated with changes
in slope. A profile survey which records only breakpoint stations can have
equivalent (or even better) information to a survey which records a regularly
spaced set of stations, but with fewer entries (and less time in the field).
- Control Points
- Control Points
are fixed points of known coordinates. Such information
can give only elevation or can include all coordinates. Control points are
determined by high-accuracy surveys.
- In a less rigorous sense, control points for a construction project can be
established conveniently around the project area using high-accuracy
procedures. Such points would then be used throughout the project for
referencing subsequent survey work, such as locating foundations, pipes, etc.
- Cut Tape
- A cut tape has the last major division at the head subdivided into
finer graduations, usually in tenths of a foot (or meter), sometimes in
hundredths. The use of this tape requires that the minor reading be subtracted
from the major division reading.
- Some tapes have minor divisions at both the head and tail.
- Datum
- A datum is a fixed starting point of a scale. For example, the
datum-level for elevation is typically taken as mean sea level. The datum for
latitude is the prime meridian (through the Royal Observatory in Greenwich,
England).
- Every datum is arbitrary. However, judicious selection of a datum can make
life easier.
- Electronic Distance Measurement, EDM
- EDM is a relatively new technique that is still evolving and improving. It
was first introduced in 1948 by Swedish physicist Erik Bergstrand. His device
used visible light and could accurately measure distances up to 25 miles at
night. First introduced in 1957, microwave instruments can be used day or
night.
- Current devices are either electro-optical instruments, which use
laser or infrared light, or microwave instruments. The former requires
a passive reflector at the opposite end of the line, while the latter method
requires two identical instruments. Refer to the texts for more information on
EDM.
- Field Books
- Field books are standard forms for recording of survey data as it is
collected. There are different types of field books that are common for
different types of surveys.
- The pages of a field book are typically numbered in pairs, i.e., the left
and right pages that face each other are given one number and are considered
as a unit containing related information.
- The left side of the 'page' is usually ruled into six columns (some books
have eight columns). The right 'page' usually looks like a sort of graph
paper. This is where most of the differences occur. Various types are:
transit, engineer's, cruiser's, leveling, etc. (Look at a catalog like
Forestry Supply or Ben Meadows for details.)
- The transit
book is very commonly used and is recommended for class use.
- Field Notes
- Field notes are a permanent record of field procedures and the data
collected in those procedures. Field notes should be made carefully. It is a
common tendency to crowd information onto the pages. Paper is cheap.
Information isn't. Do not crowd information onto the page. Make entries
distinct so that you will be able to retrieve what you went out to find.
-
- Use a medium-hardness pencil to obtain a clean, clear marking of data.
-
- Print all entries neatly. Usage of case should be consistent throughout.
-
- All computations should be checked and signed by the members of the
survey team.
-
- Sketches should be drawn to approximate scale with care taken to
preserve the relative positions and orientations of features.
-
- Orient the sketch so that North will be toward the top of the page.
Always include an arrow indicating North on the sketch.
-
- Straightedges and curve templates are recommended for all line work. The
improvement in clarity is worth the additional time required to make the
sketch neatly.
-
- Mistakes in the entry of measured data cannot be erased. Line it
out carefully and enter the correct value adjacent to it (even using another
line, if necessary :-).
-
- Mistakes in other entries, such as calculated values, drawings, etc.,
may be cleanly erased and reentered.
-
- Notes that are copied (from another page or any other source) must be
clearly labeled as copied. It is unethical to represent copies as field
notes.
-
- Text entries on the sketch should read from the bottom or the right hand
side. Consistency is appreciated.
-
- Note takers should verify all data by repeating it as it is written
down. The team member making the measurements should listen as the numbers
are called back and confirm their accuracy.
-
- Record data with appropriate precision. For example, if a length is
measured to the hundredth of a foot, write it that way. Do not drop trailing
zeros, etc., that communicate the precision of the measurement.
-
- Enter data in the order in which they are collected to preserve the
interdependencies of the measurements.
-
- If a page is to be "scrapped", write VOID across it, along with a
diagonal line. Include a reference to the page where the data can now be
found.
- Foresight
- A foresight is a reading taken on a position of unknown
coordinate(s). Since a survey progresses from a point of known position to
points of unknown position, a foresight is a reading looking "forward" along
the line of progress. Foresights may be taken on the "main circuit" of the
survey or on additional points of interest. Readings on additional points of
interest are sometimes called sideshots or intermediate
foresights to distinguish them from the readings that form the main
circuit of the survey.
- (Compare to backsight).
- Hand Level
- A hand level is a small scope fitted with a spirit level that is visible
while looking through the scope. It is used to make rough estimates of
relative elevations.
-
- Magnetic Declination
- Magnetic declination is the horizontal angle between true north (i.e., the
geographic meridian) and magnetic north (i.e., the magnetic meridian).
- There are two conventions for specifying the angle. One is to indicate the
magnitude (e.g., 6o) and direction as E or W of north. The other
considers positive values to be toward the east and negative values to be
toward the west.
- Magnetic declination is dynamic. It changes over time as the earth's
magnetic field changes. There is a more or less orderly tendency to shift
about the same amount per year (as much as 5-10 minutes!). There are also
cyclical fluctuations on yearly (about 1') and daily (about 8') periods.
The direction and rate of drift vary over time, so you should use
information on magnetic declination and drift from as close to the time of a
survey as possible. Long term records from London show a variation of 16
degrees over four centuries.
- Magnetic declination is usually indicated on maps in the area of the
legend.
- For a start into further investigations, see the NGDC Geomagnetism Home Page.
- Meridian
- A north-south reference line. It may be taken through the position of the
instrument, or, in special cases, through a reference point (such as the Royal
Observatory in Greenwich, England, which designates the Prime Meridian -
0o longitude).
- Nadir
- The nadir is that part of the celestial sphere that is directly below the
observer. For a transit or theodolite, it is the point directly below the
vertical axis of the instrument. (Compare to zenith.)
- Occupied Point
- The physical point over which the instrument (level, transit, total
station, etc.) is set up. It is the point from which any measurements taken
while at that point are reckoned. Often abbreviated in notes as
OC.
- Orders of Surveys
- The order of a survey is a way of expressing the accuracy of the
work. The order of the survey can have two levels of designators, namely,
Order and Class.
- Leveling:
The Federal Geodetic Control Subcommittee recommends the
following formula for allowable misclosures:

- where C is the misclosure, in millimeters; m is a constant;
and K is the total length leveled, in kilometers.
|
Order of Survey |
m |
| First-order Class I |
4 mm |
| First-order Class II |
5 mm |
| Second-order Class I |
6 mm |
| Second-order Class II |
8 mm |
| Third-order |
12 mm |
- Pacing
- Pacing is a "quick and dirty" method for estimating distances. One simply
walks from one point to another, counting steps. Knowing the length of one's
step allows a quick estimation of the distance. With practice, pacing
estimates will typically be accurate to within 2%.
- Pacing is most reliable on even terrain without obstructions. The more
uneven or unstable the surface (such as plowed ground or loose sand), the
lower the accuracy. Pacing upslope tends to shorten the step and pacing
downslope tends to lengthen the step. If better accuracy is required, use
another method.
- Plane Surveying
- Plane surveying is a subset of the general field of surveying in which it
is assumed that a Cartesian coordinate system is applicable or appropriate.
The methods of plane surveying are appropriate for most construction and
planning tasks that are relatively small in scale.
- Plane surveying is used to approximate the conditions on small portions of
the surface of the earth (which is, of course, spherical). You must assess the
amount of curvature that will be involved in a project and make the judgment
as to whether or not it can be ignored, or what sort of corrective procedures
should be incorporated.
- Plumb Bob
- A plumb bob is carefully machined, pointed weight that is suspended with a
string. It is used to indicate a (local) vertical line through the point of
suspension.
- Plumb bobs are commonly used for locating an instrument precisely over a
fixed point or to project a vertical line between a tape and a point on the
ground.
- Reduction of Notes/Data
- "Reducing notes" or "Reduction of data" is the process of extracting the
desired information from the field notes, i.e., the measurements and
accompanying notes that were made in the field. This is usually done in the
office, but portions may need to be done in the field to check the accuracy of
work before leaving the site.
- Rod
- A rod is essentially a stick with precise markings on it. A variety of
rods are available, which have specialized markings for various tasks. Refer
to a surveying text for more detail.
- The most commonly used rod is the Philadelphia rod, which is
marked in feet, tenths, and hundredths. With care, and a vernier attachment,
readings can be obtained to the thousandth of a foot. Feet are typically
marked with large, red numerals, with tenths marked with smaller, black
numerals. Each bar is 0.01 ft wide. The longer sides of the pointed bars mark
multiples of 0.05 ft.
- The rod may be marked on both sides - with scales in opposite directions.
Make sure you are looking at the correct side for the type of reading you want
to make.
- Rods usually have two or more sections so that they can be shortened for
ease of handling and transport. When using the rod in an extended position,
make sure the extension is fully extended and locked into place (or you may
get some peculiar readings).
- Section of a Philadelphia Rod:
- For very precise work, special rods are available. These have the scales
marked on invar strips. (See Tapes/Taping
for more detail about invar.) Precision rods are equipped with bubble levels
and braces to help hold the rod plumb and steady.
-
-
- Sideshot or Intermediate Foresight
- A shot onto an unknown point which is not a station on
the traverse.
Sideshots (or intermediate foresights) are booked in the same way as regular
foresights onto traverse stations, but are not included in the calculations
for vertical error of closure.
- Sketch
- A good sketch is invaluable. It will help to explain the job and show the
orientations of various important features. It is definitely worth taking a
few minutes to produce a good sketch.
When you arrive at the job site, size
up the whole thing. How is the job situated with respect to permanent features
in the area (roads, buildings, streams, fences, trees, etc.)? Begin by noting
the permanent (or nearly so) features around the perimeter (and within) the
job site. Drawing these provides a "frame" for the rest of the sketch.
Then draw in the details of the job site. If greater detail
is needed than can be shown at that scale, use auxiliary sketches (on
following pages, if necessary) to get the important features
recorded.
(Preserving the approximate scale helps to communicate relative
orientations, but it is not an absolute requirement. Distortions in portions
of a sketch can illuminate helpful details. Whether or not you use an
auxiliary sketch is a judgement call on your part. Which will provide the
clearer picture?)
Always make the sketch with North at (or
near) the top (or left side) of the page. Put an arrow with an "N" on the
sketch to indicate North. Include the scale of the drawing. Be reasonably
precise.
Since every
survey job involves a sequence of measurements, you must
indicate what you use for reference points. THESE ARE IMPORTANT! The survey is
worthless if it cannot be repeated, and it cannot be repeated if the reference
points are not identified explicitly! Detailed descriptions
of each reference point must be included with the sketch.
How
detailed? The description must contain enough information
that someone else, who is not at all familiar with
the site, could locate the exact points with relative ease. Since many of the
measurements will be made to the hundredth (or even thousandth) of a foot, the
descriptions must be very clear. There is no room for ambiguity!
One
advantage of doing a proper sketch is that it forces you to look at the whole
job before you start taking measurements. Looking over the job site, you will
be able to plan your survey to make the strongest set of measurements with the
least amount of effort. A few minutes invested up front can save a lot of time
later on.
- Stadia Tables
- Stadia tables are compilations of the solutions of the equations for
inclined stadia. With the vertical angle reading, one can enter the table and
find factors which are multiplied by the rod interval (difference in readings
between the upper and lower cross-hairs) to obtain the horizontal distance and
elevation difference between the instrument and the rod. A table (with very
small type) can be viewed/printed from here.
- Staking
- The placement of markers on a site to identify certain locations (such as
the corners of a building, the right-of-way of a road, the extent of the slope
faces of a dam, etc.) with corresponding information (such as cut or fill for
earthmoving) is the process of staking out a project. It is the transferal of
information from the plan to the actual site --- in a manner that the work
crews will understand and use. It is therefore very important that the
information be as simple and as clear as possible.
- There are many conventions and methods for staking and marking. The
particular practice will depend on the type of job and the type of information
that must be communicated.
- Staking must often be done several times during a project as various
phases of the work will "erase" these temporary markers.
- Stations
- The term station refers to a point on a baseline that is at a known
distance from a starting/reference point. The starting point is usually
referenced as 0 + 00, but there are occasions where another value
might be assigned. It is generally desirable to have all stations noted by
positive numbers, since negative stations often lead to confusion of
interpretation. Full stations are at integer multiples of some base
distance - usually 100 feet or 100 meters. The numeral to the left of the "+"
indicates the multiples of the base distance and the numeral on the right
indicates numbers less than the base distance.
- For example, if the starting point was designated 0+00, a point
375.62 feet away (following the baseline) would be noted as 3+75.62.
- The term "station" is also used more loosely to indicate any point used in
a survey, such as benchmarks and turning points. As in so many aspects of
language, context is important.
- Tapes/Taping
- A tape is a flexible device used for measuring linear distances. There are
tapes made of many materials, such as cloth, kevlar, steel, and invar. The
most common tape used by surveyors is the steel tape. Standard lengths are 100
feet (for English unit surveys) or 30 meters (for SI unit surveys).
- Tapes are usually marked at every foot or meter. At the ends of the tape,
there will be finer divisions (tenths/hundredths of a foot, or
decimeters/centimeters). Tapes are called "add" tapes if the finer divisions
are in a major unit beyond the ends of the regular length, e.g., beyond
the zero and 100-ft marks of an English tape. If, on the other hand, the
divisions are marked inside the last major units, the tape is called a
"cut" tape. E.g., the decimeter/centimeter divisions are marked between the
zero and one-meter marks and between the ninety-nine and one hundred meter
marks.
- For high precision surveys, invar tapes are useful. Invar is a nickel-steel alloy that has a coefficient of thermal
expansion of 2.0x10-7 to 5.5x10-7 per °Fahrenheit.
Regular steel tapes have a coefficient of thermal expansion of
64.5x10-7 per °Fahrenheit, or 116x10-7 per °Celsius.
- Traverse
- A traverse is a series of consecutive line segments whose lengths
and directions are determined by field measurements. A closed traverse
either closes back upon its starting point, or begins and ends on stations of
known positions. An open traverse does not close on either itself or a
station of known position. As such, an open traverse does not provide any
means for checking for errors and mistakes. Open traverses should generally be
avoided. If an open traverse must be used, the procedure should be repeated to
provide a check of accuracy.
- Turning Point
- A turning point is a station, either temporary or permanent, that
is used as a pivot between sequential instrument positions. Since a turning
point is used to extend the primary survey, its elevation must be precisely
recoverable (at least for the time it takes to move the instrument and take a
backsight on it). A spot on rough ground (e.g., a plowed field) is
unacceptable. A mark on pavement, a rock face, top of a fence post or fire
hydrant would be good. Surveyors will often carry stakes that can be driven
into the ground to provide a temporary solid surface for a turning point.
- Vertical Error of Closure
- The error of closure of a leveling survey refers to the cumulative error
of the entire circuit. If a circuit is run from a point of known (or assumed)
elevation back to that point, then the starting elevation and the ending
elevation should be the same. In actual practice, errors are made in
measurements that result in a discrepancy between the two values. That
discrepancy, expressed as a raw vertical distance (in units such as feet or
meters), is the error.
- The allowable error in any such survey depends on the level of accuracy
required for the job. Various levels are accuracy are required for different
orders
of surveys.
- Zenith
- The zenith is that point of the celestial sphere that is directly overhead
from the observer. For a transit or theodolite, it is the point directly above
the vertical axis of the instrument. (Compare to nadir.)