Level II scour analysis for Bridge 7H (HUNTTH0001007H) on Town Highway 1, crossing Cobb Brook, Huntington, Vermont

Open-File Report 97-339
Prepared in cooperation with Vermont Agency of Transportation and Federal Highway Administration
By:

Links

Abstract

This report provides the results of a detailed Level II analysis of scour potential at structure HUNTTH001007H on Town Highway 1 crossing the Cobb Brook, Huntington, Vermont (figures 1–10). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.

In August 1976, Hurricane Belle caused flooding at this site which resulted in road and bridge damage (figures 7-8). This was approximately a 25-year flood event (U.S. Department of Housing and Urban Development, 1978). The site is in the Green Mountain section of the New England physiographic province in central Vermont. The 4.20-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest upstream of the bridge. Downstream of the bridge is brushland and pasture.

In the study area, the Cobb Brook has an incised, straight channel with a slope of approximately 0.03 ft/ft, an average channel top width of 43 ft and an average bank height of 6 ft. The channel bed material ranges from sand to boulders with a median grain size (D50) of 65.5 mm (0.215 ft). The geomorphic assessment at the time of the Level I and Level II site visit on June 24, 1996, indicated that the reach was stable.

The Town Highway 1 crossing of the Cobb Brook is a 23-ft-long, two-lane bridge consisting of one 20-foot concrete slab span (Vermont Agency of Transportation, written communication, June 21, 1996). The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 15 degrees to the opening while the opening-skew-to-roadway is zero degrees.

A scour hole 2.8 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. Protection measures at the site include type-1 stone fill (less than 12 inches diameter) at the downstream right wingwall, type-2 stone fill (less than 36 inches diameter) at the upstream right wingwall and the downstream end of the downstream left wingwall, and type-3 stone fill (less than 48 inches diameter) at the upstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.

Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.

Contraction scour for all modelled flows ranged from 0.2 to 1.3 ft. The worst-case contraction scour occurred at the incipient-overtopping discharge. Abutment scour ranged from 4.0 to 8.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 10. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.

It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Study Area

Publication type Report
Publication Subtype USGS Numbered Series
Title Level II scour analysis for Bridge 7H (HUNTTH0001007H) on Town Highway 1, crossing Cobb Brook, Huntington, Vermont
Series title Open-File Report
Series number 97-339
DOI 10.3133/ofr97339
Year Published 1997
Language English
Publisher U.S. Geological Survey
Publisher location Pembroke, NH
Description iv, 51 p.
Country United States
State Vermont
City Huntington
Other Geospatial Cobb Brook
Scale 24000
Google Analytic Metrics Metrics page
Additional publication details