Level II scour analysis for Bridge 3 (EASTTH00010003) on Town Highway 1, crossing the East Branch Passumpsic River, East Haven, Vermont
Links
- Document: Report
- Download citation as: RIS | Dublin Core
Abstract
This report provides the results of a detailed Level II analysis of scour potential at structure EASTTH00010003 on Town Highway 1 crossing the East Branch Passumpsic River, East Haven, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.
The site is in the White Mountain section of the New England physiographic province in northeastern Vermont. The 50.4-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover on the left bank upstream is forest. On the remaining three banks the surface cover is pasture while the immediate banks have dense woody vegetation.
In the study area, the East Branch Passumpsic River has an incised, sinuous channel with a slope of approximately 0.003 ft/ft, an average channel top width of 62 ft and an average bank height of 5 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 61.5 mm (0.187 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 14, 1995, indicated that the reach was stable.
The Town Highway 1 crossing of the East Branch Passumpsic River is a 89-ft-long, two-lane bridge consisting of one 87-foot steel-beam span (Vermont Agency of Transportation, written communication, March 17, 1995). The opening length of the structure parallel to the bridge face is 84.7 ft. The bridge is supported by vertical, concrete abutments with sloped stone fill in front that creates a spill through embankment. The channel is skewed approximately zero degrees to the opening and the opening-skew-to-roadway is also zero degrees.
Channel scour 0.5 ft deeper than the mean thalweg depth was observed to the left of the center of the channel under the bridge during the Level I assessment. The scour countermeasures at the site are type-2 stone fill (less than 36 inches diameter) along the downstream left bank and type-4 stone fill (less than 60 inches diameter) in front of the abutments creating spill through slopes. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.
Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.
Contraction scour for all modelled flows ranged from 0 to 1.8 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 6.4 to 11.7 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.
It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.
Study Area
Publication type | Report |
---|---|
Publication Subtype | USGS Numbered Series |
Title | Level II scour analysis for Bridge 3 (EASTTH00010003) on Town Highway 1, crossing the East Branch Passumpsic River, East Haven, Vermont |
Series title | Open-File Report |
Series number | 97-759 |
DOI | 10.3133/ofr97759 |
Year Published | 1997 |
Language | English |
Publisher | U.S. Geological Survey |
Publisher location | Pembroke, NH |
Description | iv, 48 p. |
Country | United States |
State | Vermont |
City | East Haven |
Other Geospatial | Passumpsic River |
Scale | 24000 |
Google Analytic Metrics | Metrics page |