Level II scour analysis for Bridge 36 (STOWTH00430036) on Town Highway 43, crossing Miller Brook, Stowe, Vermont

Open-File Report 97-780
Prepared in cooperation with Vermont Agency of Transportation and Federal Highway Administration
By:  and 

Links

Abstract

This report provides the results of a detailed Level II analysis of scour potential at structure STOWTH00430036 on Town Highway 43 crossing the Miller Brook, Stowe, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.

The site is in the Green Mountain section of the New England physiographic province in north central Vermont. The 5.5-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is predominantly forested.

In the study area, the Miller Brook has an incised, sinuous channel with a slope of approximately 0.03 ft/ft, an average channel top width of 43 ft and an average bank height of 7 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 70.4 mm (0.231 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 15, 1996, indicated that the reach was stable.

The Town Highway 43 crossing of the Miller Brook is a 24-ft-long, two-lane bridge consisting of one 21-foot steel-beam span (Vermont Agency of Transportation, written communication, October 13, 1995). The opening length of the structure parallel to the bridge face is 21.5 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 10 degrees to the opening and the computed opening-skew-to-roadway is also 10 degrees.

The footing on the left abutment was exposed 2.5 ft and the footing on the right abutment was exposed 3.0 ft during the Level I assessment. Scour protection measures at the site were type-4 stone fill (less than 60 inches diameter) on the left and right bank upstream, type-3 stone fill (less than 48 inches diameter) along the entire base length of the upstream right wingwall, right abutment, and type-2 stone fill (less than 36 inches diameter) along the entire base length of the downstream right wingwall, and left and right banks downstream. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.

Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.

Contraction scour for all modelled flows ranged from 0.0 to 0.9 ft. The worst-case contraction scour occurred at the 500-year discharge. Abutment scour ranged from 3.1 to 6.5 ft. The worst-case abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.

It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Study Area

Publication type Report
Publication Subtype USGS Numbered Series
Title Level II scour analysis for Bridge 36 (STOWTH00430036) on Town Highway 43, crossing Miller Brook, Stowe, Vermont
Series title Open-File Report
Series number 97-780
DOI 10.3133/ofr97780
Year Published 1997
Language English
Publisher U.S. Geological Survey
Publisher location Pembroke, NH
Description iv, 51 p.
Country United States
State Vermont
City Stowe
Other Geospatial Miller Brook
Scale 24000
Google Analytic Metrics Metrics page
Additional publication details