Level II scour analysis for Bridge 53 (CAMBTH00750053) on Town Highway 75, crossing the Brewster River, Cambridge, Vermont
Links
- Document: Report
- Download citation as: RIS | Dublin Core
Abstract
This report provides the results of a detailed Level II analysis of scour potential at structure CAMBTH00750053 on Town Highway 75 crossing the Brewster River, Cambridge, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D.
The site is in the Green Mountain section of the New England physiographic province in northwestern Vermont. The 4.30-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is forest, except for the downstream right overbank area which has a barn surrounded by grass and shrubs.
In the study area, the Brewster River has an incised, straight channel with a slope of approximately 0.05 ft/ft, an average channel top width of 62 ft and an average bank height of 12 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 84.4 mm (0.277 ft). The geomorphic assessment at the time of the Level I and Level II site visit on July 11, 1995, indicated that the reach was stable.
The Town Highway 75 crossing of the Brewster River is a 28-ft-long, two-lane bridge consisting of one 24-foot concrete tee-beam span (Vermont Agency of Transportation, written communication, March 8, 1995). The opening length of the structure parallel to the bridge face is 22.4 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 40 degrees to the opening while the opening-skew-to-roadway as surveyed is 10 degrees.
A scour hole 1 ft deeper than the mean thalweg depth was observed along the left abutment during the Level I assessment. The scour counter-measures at the site included type-3 stone fill (less than 48 inches diameter) along the entire base length of the upstream left wingwall. There was also type-4 stone fill (less than 60 inches diameter) along the downstream end of the downstream right wingwall. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E.
Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995). Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.
Contraction scour for all modelled flows ranged from 1.1 to 1.4 ft. The worst-case contraction scour occurred at the 100-year discharge. Abutment scour ranged from 10.7 to 17.3 ft. The worst-case abutment scour occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.
It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and others, 1995, p. 47). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.
Study Area
Publication type | Report |
---|---|
Publication Subtype | USGS Numbered Series |
Title | Level II scour analysis for Bridge 53 (CAMBTH00750053) on Town Highway 75, crossing the Brewster River, Cambridge, Vermont |
Series title | Open-File Report |
Series number | 97-647 |
DOI | 10.3133/ofr97647 |
Year Published | 1997 |
Language | English |
Publisher | U.S. Geological Survey |
Publisher location | Pembroke, NH |
Description | 50 p. |
Country | United States |
State | Vermont |
City | Cambridge |
Other Geospatial | Brewster River |
Scale | 24000 |
Google Analytic Metrics | Metrics page |